The Next Generation in Australian Steel Starts Here

The next generation of Australian steel.

Generation Steel is advancing the next generation of steel manufacturing in Australia, converting 100% Australian scrap steel into high quality low emission steel for customers who need quality, Australian-made steel at a competitive price. Most steel used in Australia today is imported. Generation Steel is changing that with a modern electric arc furnace mill, fed by Australian scrap steel, to produce rebar, coil and a range of merchant bar products at a quality and price that competes directly with imports with the added benefits of being some of the lowest emission steel produced globally and supporting high quality jobs locally.

An Australian project built to supply the market nationally.

Major milestones on the path to first steel.

Follow the project’s progress toward Australia’s first new steel mill in 35 years.

27 AUG 2025

Grid connection

Western Power Access Offer received for connecting the Collie Steel Mill to the WA grid (with GHD and DEED). Described as Australia’s first new steel mill in over 30 years.

3 SEP 2025

Renewable power

PPA Term Sheet executed with Tonic Renewables — up to 134,000 MWh/yr of clean energy from the Binningup Solar and Battery facility.

17 SEP 2025

Energy storage

Partnership with NHOA Energy for power and storage; pairs Danieli Q-One furnace technology with grid-scale battery expertise (Kwinana BESS).

1 OCT 2025

Japan trade mission

Executive Director Azlan Ho joined Premier Roger Cook’s WA Government delegation to World Expo Osaka and Tokyo, presenting the Collie project to Japanese investors.

15 OCT 2025

South32 MOU

MOU signed with South32 Worsley Alumina to recycle scrap steel from its operations through the Collie Steel Mill.

12 NOV 2025

WA procurement

WA Government announces that State projects will be built with WA-made green steel, backed by ‘if not, why not’ procurement rules, a steel addendum to the WA Industry Participation Strategy and a green steel expression of interest process.

3 DEC 2025

Lendlease

MOU with Lendlease for Australian-made, 100% recycled, ultra-low emissions rebar.

15 DEC 2025

National logistics

Partnership with Prime Global Logistics as logistics management partner; national backhaul-freight distribution strategy WA to NSW/SA/VIC.

13 FEB 2026

Laing O’Rourke MOU

Laing O’Rourke announced a non-binding MOU with Generation Steel for Australian-made low emission rebar at scale.

13 MAR 2026

Birdon MOU

Scrap supply MOU with Birdon Pty Ltd — ferrous scrap from maritime/offshore decommissioning (ex-HMAS Sirius, ex-HMAS Otama, oil and gas assets).

15 APR 2026

CCR partnership

Partnership with CCR (Climate Change Response) — sustainability, energy and climate intelligence platforms for 50-100 year asset resilience.

JUN 2026

Executive Chairman appointed

Enzo Gullotti, a 35-year veteran of the Australian construction industry, appointed Executive Chairman of Generation Steel.

12 JUN 2026

WA Government investment

WA Government commits $9.8 million in pre-development funding through the Collie Industrial Transition Fund, with support from the ACTU and AMWU.

26 JUN 2026

Industry recognition

Australian Steel Institute profile: Danieli EAF technology; product range of rebar, wire rod, coil and merchant bar.

23 JUL 2026

$850M expansion

Project grows to $850M with a new Cut and Bend facility and a partnership with Stride Reinforcement; 450,000 tpa rebar, 100% renewable energy and Australian recycled scrap.

9 AUG 2026

Federal recognition

The Net Zero Economy Authority highlights the project’s $40 million Cut and Bend expansion, its new national supply partnerships and its 450,000 tonnes a year capacity.

12 AUG 2026

Leadership appointments

Lachlan Roberts (Project Director), Karl Matacz (CFO, formerly CFO of Synergy) and Moksha Watts (Executive Director, formerly the Prime Minister’s adviser on climate change, energy and resources).

NEXT

Final Investment Decision

FORTHCOMING

Forthcoming

Building for the future.

Australian scrap, Australian steel

The mill runs on 100% Australian recycled scrap steel, removing any reliance on imported virgin material.

Our model

Proven technology

Danieli’s Q-One electric arc furnace and MIDA rolling mill technology, already operating in mills worldwide, brought to Australia.

Technology

Lower emissions, built into the process

Recycled inputs and 100% renewable energy from day one. The reduction comes from how the mill runs, not from a claim on a page.

Our approach

250 direct jobs

~500 construction roles to build the mill, ~250 ongoing positions to run it, in a town that has powered Western Australia for a century.

The project

From scrap to steel, on one site.

Australian scrap steel arrives on site, is melted in an electric arc furnace, continuously cast and rolled into finished steel, then dispatched to projects across Australia and available for export markets that are demanding low emission steel products.

Architectural render of the Generation Steel mill, with six numbered process locations.

Australian scrap is collected from demolition, industrial, manufacturing and infrastructure streams.

Working across the value chain

We collaborate with partners across the steel and construction ecosystem, and welcome engagement from organisations building the next generation of Australian industrial capability.

Feedstock & Materials

Australian scrap steel supply

Energy & Infrastructure

Renewable power and grid partners

Logistics & Distribution

National freight networks

Construction & Delivery

Builders and reinforcement customers

Publicly announced partners and collaborators

Western Power, Tonic Renewables, NHOA Energy, South32, Lendlease, Laing O’Rourke, Birdon, CCR, Stride Reinforcement

Established worldwide.

The mill runs on Danieli technology, already in operation at plants around the world. Proven, bankable technology.

EstablishedDanieli EAF technology operates across hundreds of plants globally.

AutomatedModern process control delivers a consistent, certifiable, low emission product.

Built to repeatA model designed to extend to future sites.

BankableBacked by proven technology, not projected performance.

News and project updates

All news